This summer Vista Grande has under gone some major renovations. In classroom buildings 100 and 200 new roofs and mechanical screens were installed; HVAC equipment was replaced;   ducts were cleaned and energy management controls were upgraded.  In building 300 an existing storage room was converted into a new restroom.  The campus also received significant site work.  Existing concrete and asphalt had numerous tripping hazards and have been removed and replaced.  ADA parking and drop off improvements were also addressed in this phase. Exterior lighting has been upgraded along with the fire alarm.  New classroom doors, windows, carpeting, data and paint will be addressed next summer.
 
Feb-Mar 2017
Facilities Assessment report in progress.
 
Summer 2019
Isolated abatement
 
  • Replace flooring  in rooms not previously replaced
  • New windows
  • New doors and frames
  • Data upgrades
  • New lights in classrooms
  • Fire alarm upgrades
  • New ceiling tile
  • ADA upgrades in building 100
  • Replace marker boards
  • Center projectors in center of teaching wall
Vista Grande Elementary Modernization
Construction Start Date: June 3, 2018
Construction End Date: July 31, 2019
Architect: ATI Architects & Engineers
 
Contractor: S & H Construction
Budget: $3.3 million
 
Project Manager: Russ Brooking